AWS D1.1 is the structural steel welding code published by the American Welding Society. It governs how structural steel gets welded in buildings, bridges, and other load-bearing structures across North America. If you’re welding structural steel in the U.S., D1.1 is the code you’ll work under, and understanding it separates qualified structural welders from everyone else.

The code covers everything from joint design and welding procedures to welder qualification and inspection requirements. It applies to carbon and low-alloy steels with minimum yield strengths up to 100 ksi. It does not cover pressure vessels (that’s ASME), pipeline work (API 1104), or non-ferrous metals.

Scope and Application

AWS D1.1 applies to welded connections in structural steel. That includes rolled shapes, built-up members, plate girders, trusses, and connections between these elements. The code applies to both shop fabrication and field erection.

The Engineer of Record (EOR) has final authority on all welding-related decisions. D1.1 makes this clear throughout the code. The EOR can impose requirements beyond D1.1 minimums, accept or reject deviations, and specify additional testing. The contractor can’t override the EOR’s decisions.

What D1.1 Does NOT Cover

  • Pressure vessels and boilers (ASME Section VIII and IX)
  • Process piping (ASME B31.3)
  • Pipelines (API 1104)
  • Sheet metal under 1/8 inch thick
  • Aluminum, stainless steel, or other non-carbon steels (separate AWS codes exist for these)
  • Base metals with yield strength over 100 ksi

Prequalified vs. Qualified WPSs

This distinction trips up a lot of people. D1.1 provides two paths for establishing a Welding Procedure Specification (WPS).

Prequalified WPSs (Clause 3)

A prequalified WPS uses joint designs, welding processes, and parameters listed in the code’s tables and figures. If your procedure fits within these established parameters, you don’t need to run a procedure qualification test. You still need a written WPS document, but you skip the PQR testing.

Prequalified conditions include:

  • Processes: SMAW, SAW, GMAW (except short-circuit transfer), FCAW
  • Joint designs: Must match the prequalified joint details in Clause 3, including groove angles, root openings, and root faces
  • Base metals: Listed prequalified base metals in Table 3.1
  • Filler metals: Must match the base metal strength group
  • Preheat: Must meet Table 3.3 minimums

Short-circuit GMAW (common shop MIG) is NOT prequalified. If you’re using short-circuit transfer, you need a qualified WPS backed by testing.

Qualified WPSs (Clause 4)

If your procedure falls outside prequalified parameters, you need to qualify it through testing. This involves welding test plates per the proposed WPS, cutting test specimens, and performing destructive tests (bend tests, macro-etch, tensile tests depending on the joint type).

The test results get documented in a Procedure Qualification Record (PQR). The PQR backs the WPS and proves the procedure produces sound welds.

FeaturePrequalified WPSQualified WPS
Testing requiredNo PQR testingPQR with destructive testing
Joint designsMust match Clause 3 detailsAny joint design
Processes allowedSMAW, SAW, GMAW (spray/glob), FCAWAny process
Short-circuit GMAWNot allowedAllowed with qualification
Written WPS requiredYesYes
CostLower (no test plates)Higher (materials + testing lab)

Welder Qualification Testing (Clause 9)

Every welder working under D1.1 must pass a performance qualification test. This test proves the welder can produce sound welds in specific positions using specific processes. It’s separate from the WPS qualification; the WPS proves the procedure works, and the welder qualification proves the person can execute it.

Test Positions and Qualification Range

D1.1 uses the standard position designations:

  • 1G/1F: Flat groove/fillet
  • 2G/2F: Horizontal groove/fillet
  • 3G/3F: Vertical groove/fillet
  • 4G/4F: Overhead groove/fillet
  • 5G/6G: Pipe positions (covered under pipe qualification)

The key to D1.1 Table 9.10 is understanding which test positions qualify you for which production positions:

Test TakenPositions Qualified
1G plateFlat only
2G plateFlat, horizontal
3G plateFlat, horizontal, vertical
4G plateFlat, overhead
3G + 4G plateAll positions (flat, horizontal, vertical, overhead)

The 3G + 4G combination is the standard path for full plate qualification. Most structural shops require this as a minimum for new hires.

Test Plate Requirements

Standard plate test specimens use 3/8 inch material, 7 inches wide, with a single-V groove joint. The bevel angle is typically 22.5 degrees per side (45 degrees included), with a 1/4 inch root opening and backing strip. Some tests use open-root configurations without backing.

Essential Variables for Welder Qualification

If a welder changes any of these, they need to requalify:

  • Welding process (SMAW to GMAW, etc.)
  • Electrode/wire classification change that crosses groups
  • Position change beyond qualified range
  • Backing removed (backing to open root)
  • Single-pass fillet welds over 1/2 inch in a single pass (if not previously qualified)

Qualification Expiration

D1.1 welder qualifications don’t expire on a calendar date, but they do lapse. If a welder hasn’t used a specific process for more than 6 months, their qualification for that process lapses. The qualification can be renewed by welding a single test specimen, not a full requalification.

Visual Inspection Acceptance Criteria (Clause 8)

Visual inspection (VT) is required on 100% of all production welds. D1.1 Clause 8 defines what’s acceptable and what requires repair.

Statically Loaded Structures

DefectAcceptance Criteria (Static)
CracksNone permitted, any size or location
Incomplete fusionNone permitted
Undercut1/32 in max depth
PorositySum of diameters shall not exceed 3/8 in per linear inch
Reinforcement (groove welds)1/8 in max for material up to 2 in thick
Fillet weld sizeMeet minimum per drawing, max undersize 1/16 in for 10% of length
Arc strikesMust be removed by grinding

Cyclically Loaded Structures

Cyclically loaded structures (bridges, crane runways, structures subject to fatigue) have tighter limits. Undercut drops to 0.01 inch maximum. Porosity limits become more restrictive. Certain defect combinations that pass for static loading get rejected for cyclic loading.

Most Commonly Cited Clauses

If you’re studying D1.1 or preparing for a CWI exam, these are the sections you’ll reference most often:

Clause 3 (Prequalification): Joint details, preheat requirements (Table 3.3), filler metal requirements. This is where prequalified WPS parameters live.

Clause 4 (Qualification): WPS qualification testing, PQR requirements, essential variables. Used when procedures fall outside prequalified limits.

Clause 5 (Fabrication): The day-to-day rules. Base metal preparation, assembly tolerances, welding technique requirements, preheat and interpass temperature control, weld profiles, and repair procedures.

Clause 6 (Inspection): Inspector qualifications, inspection scope, NDT requirements. Specifies when RT, UT, MT, and PT testing are required beyond VT.

Clause 8 (Acceptance Criteria): The tables and criteria that determine pass or fail. Separate criteria for statically loaded (Table 8.9) and cyclically loaded (Table 8.11) structures.

Clause 9 (Welder Qualification): Performance qualification testing, test positions, qualification ranges, essential variables.

D1.1 in Practice: What Shops Actually Do

In a typical structural fabrication shop, D1.1 plays out like this:

  1. The engineer specifies weld sizes, joint types, and any special requirements on the drawings
  2. The shop develops WPSs matching the engineer’s requirements (prequalified wherever possible)
  3. Welders qualify on the processes and positions they’ll use in production
  4. QC inspects every weld visually, plus NDT on welds the code or engineer requires
  5. Documentation stays on file: WPSs, PQRs, welder continuity logs, inspection reports

The biggest compliance failures I see in shops are documentation gaps. The welding itself is fine, but the WPSs are missing or outdated, welder qualification records are incomplete, or nobody’s tracking the 6-month continuity requirement. An auditor doesn’t just check your welds; they check your paperwork.

Preheat Requirements (Table 3.3)

Preheat prevents hydrogen-induced cracking in the heat-affected zone. D1.1 Table 3.3 sets minimum preheat temperatures based on steel group, thickness, and welding process.

Steel GroupThicknessMinimum Preheat (SMAW with low-hydrogen electrodes)
Group I (A36, A992)Up to 3/4 in32F (0C) - none required above freezing
Group I3/4 to 1-1/2 in150F (66C)
Group I1-1/2 to 2-1/2 in225F (107C)
Group IOver 2-1/2 in300F (149C)
Group II (A572 Gr 50)Up to 3/4 in32F (0C)
Group II3/4 to 1-1/2 in150F (66C)
Group II1-1/2 to 2-1/2 in225F (107C)
Group IIOver 2-1/2 in300F (149C)

Non-low-hydrogen processes (E6010, E6013, E7024) require higher preheat temperatures. The code includes separate columns for these processes. Using low-hydrogen electrodes (E7018) or FCAW/GMAW reduces preheat requirements.

NDT Requirements

D1.1 doesn’t require NDT on all welds. The extent of NDT depends on the connection type and loading:

  • Complete Joint Penetration (CJP) groove welds in tension: Typically require UT or RT per the engineer’s specification
  • CJP groove welds in compression: May require NDT at the engineer’s discretion
  • Fillet welds and PJP groove welds: VT only, unless the engineer specifies additional testing
  • Demand-critical welds (seismic): 100% UT per AISC 341, referenced by D1.8

The engineer of record specifies NDT requirements on the drawings or in the project specifications. D1.1 gives guidelines, but the EOR makes the call.

Common D1.1 Mistakes to Avoid

Not using low-hydrogen practices. E7018 electrodes stored in a rod oven, FCAW wire kept dry, proper preheat. Hydrogen cracking in structural steel is preventable but unforgiving.

Overwelding. Putting a 5/16 inch fillet where the drawing calls for 1/4 inch wastes material and increases distortion. It also doesn’t make the joint stronger if the connected elements aren’t designed for higher loads.

Skipping preheat on thick material. Table 3.3 exists for a reason. Cold steel plus fast cooling equals hard, brittle HAZ. That’s where cracks start.

Ignoring interpass temperature. D1.1 sets maximums (typically 600F for carbon steel) as well as minimums. Exceeding interpass temperature degrades mechanical properties.

Incomplete documentation. Keep WPSs current, maintain welder qualification records, and log continuity. The paperwork is part of the code, not optional overhead.

AWS D1.1 is a living document, updated every other year. The current edition supersedes all previous editions. Always verify you’re working from the current version, and check with your engineer or QC department when questions arise. The code gives clear answers to most structural welding questions, but it requires reading the specific clauses, not guessing.